Research on new traction system and construction technology for main cable erection of Liangqing Bridge
Author:
Affiliation:

(The Second Engineering Co., LTD., China Railway 18th Bureau Group, Tangshan 063000, China)

Clc Number:

U448.25

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    According to the characteristics of Liangqing Bridge and the situation of construction site, the main cable erection traction system is improved, and a new single-line three-stage reciprocating traction system is put forward. The application of this system greatly improves the main cable erection efficiency, shortens the construction period and guarantees the construction quality. This method provides a reference for the construction of the main cable of the long-span suspension bridge in China, and has important popularization value.

    Reference
    Related
    Cited by
引用本文

Dawei Jiang, Xiuning Peng, Yong Li, Zhen Zhang, Weixin Wang, Nianchun Deng Research on new traction system and construction technology for main cable erection of Liangqing Bridge. Prestress Technology 2017,21(05):16-21. 10.59238/j. pt.2017.05.004

复制
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:
  • Revised:
  • Adopted:
  • Online: July 25,2023
  • Published: