    Abstract:

    The Tuanhe Aqueduct project of the first phase of the Middle Route of the South-to-North Water Transfer Project has a novel structure, complex force, and the structure size ranks first among similar projects in China. It is an independent 3-channel fully prestressed concrete U-shaped thin-wall structure with a single span length of 40m and a single span weight of about 1600 t. Through the research on the prestressed construction technology of super-large cast-in-place U-shaped aqueduct, the mechanized construction of Tuanhe aqueduct body is realized, the project period is greatly shortened, and the construction cost and investment are saved.

    Reference
    Related
    Cited by
引用本文

Jianwu Xiong, Qiuyan Gao Prestressing construction technology of super-large cast-in-place U-shaped aqueduct on middle route of South-to-North Water Transfer Project. Prestress Technology 2016,20(06):14-18. 10.59238/j. pt.2016.06.002

复制
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:
  • Revised:
  • Adopted:
  • Online: August 06,2023
  • Published: