    At present, the middle arch bridge is a common urban landscape bridge. Taking Ziyang Tuojiang Bridge as an example, this paper focuses on the construction technology of gradually tensioning and dismantling of the upstream N1# and downstream N2# tie rods, and the construction technology of installing the upstream N1# and downstream N2# tie rods. Some problems in the construction of these processes are discussed.

    Reference
    Related
    Cited by
引用本文

Dehong Liao, Jianrong Tang, Yanqiao Huang Construction technology of tie rod replacement for Ziyang Tuojiang Third Bridge. Prestress Technology 2015,19(01):29-32. 10.59238/j. pt.2015.01.007

复制
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:
  • Revised:
  • Adopted:
  • Online: August 06,2023
  • Published: