悬索桥主缆索股用定型捆扎带断裂处治方案研究
作者:
作者单位:

(柳州欧维姆机械股份有限公司,柳州 545005)

作者简介:

刘杰章

通讯作者:

中图分类号:

U448.253.3

基金项目:


Study on the treatment scheme of fracture of fixed binding tape for main cable strand of suspension bridge
Author:
Affiliation:

(Liuzhou OVM Machinery Co., Ltd., Liuzhou 545005,China)

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    为分析研究悬索桥主缆索股用定型捆扎带断裂的产生原因及寻求解决措施,以南宁良庆大桥主缆为背景,采用现场生产验证对比方法,对定型捆扎带断裂关键因素进行研究。结果表明:主缆索股生产过程定型捆扎带预置缠包张力,索股上盘收线速度,索股存放时间间距、温度是定型捆扎断裂而造成索股散丝、变形、松驰等问题的关键因素,本文将针对上述原因,简述解决方案。

    Abstract:

    Based on the main cable of Liangqing Bridge in Nanning, the key factors of the breakage of the fixed binding tape were studied by using the method of field production verification and comparison. The results show that the pre-wrapping tension of the fixed binding belt, the speed of winding up of the upper wall of the cable strand, the storage time interval of the cable strand, and the temperature are the key factors that cause the loose yarn, deformation and relaxation of the cable strand in the production process of the main cable strand.

    参考文献
    相似文献
    引证文献
引用本文

Jiezhang Liu Study on the treatment scheme of fracture of fixed binding tape for main cable strand of suspension bridge. Prestress Technology 2016,20(01):33-35. 10.59238/j. pt.2016.01.006