Study on closing method of continuous rigid frame bridge with high pier
Author:
Affiliation:

(Liuzhou OVM Machinery Co., Ltd., Liuzhou 545005,China)

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    随着桥梁技术的快速发展,我国在高墩大跨连续刚构梁桥合龙施工技术方面有成熟的经验,但对于合龙顺序选择、合龙方式的选择仍是当今的两大难题,本文以沁河大桥为背景,通过对比计算来研究几种合龙方式、合龙顺序对成桥后结构受力情况的影响以及各自的适用条件,为今后的桥梁建设提供参考。

    Abstract:

    With the rapid development of bridge technology, China has mature experience in the closing construction technology of high-pier and long-span continuous rigid frame girder Bridges, but the selection of closing sequence and closing mode is still the two major problems at present. Based on the background of Qinhe Bridge, this paper studies the influence of several closing methods and closing sequence on the post-completion structure stress and their respective applicable conditions through comparative calculation It provides reference for bridge construction in the future.

    参考文献
    相似文献
    引证文献
引用本文

Wei Shi, Chang He, Weiwei Qin Study on closing method of continuous rigid frame bridge with high pier. Prestress Technology 2014,18(04):8-13. 10.59238/j. pt.2014.04.002

复制
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2023-08-06
  • 出版日期: