    (续上期) ②安装 带伸臂的立柱(7、6、5及5′、6′、7′)均采用两对葫芦同时平吊,凌空后转动吊臂居中。吊扒前移至安装节间,再缓缓松去辅助吊点,使构件翻身、垂直,然后就位安装,见图26a)、b)、c)

    Abstract:

    (Continuation of the previous period) ② The column with the extension arm (7, 6, 5 and 5 ', 6 ', 7 ') is installed with two pairs of hoists at the same time, and the lifting arm is turned in the center after the volleys. Move the lift forward to the installation node, and then slowly loosen the auxiliary lifting point to make the member turn over and vertical, and then install in place, as shown in Figure 26a), b), c).

    参考文献
    相似文献
    引证文献
引用本文

Shizhong Qiu Bridge Construction Control Technology (continued). Prestress Technology 2010,14(02):33-39. 10.59238/j. pt.2010.02.006

复制
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2023-08-06
  • 出版日期: