    摘要:

    在以往的消化池设计中多采用绕丝或低碳钢分段张拉的预应力方法。在青岛海泊河污水处理厂的4座内径28m的大型污泥消化池的设计中,为了满足耐腐蚀、抗裂(水密性和气密性)以及建立较高预压应力的要求,消化池的环向预应力首次采用无粘结预应力方案

    Abstract:

    In the previous design of digesters, the pre-stressing method of winding wire or mild steel segmental tensioning was mostly used. In the design of four large-scale sludge digesters with an inner diameter of 28 m at Qingdao Haibohe Wastewater Treatment Plant, in order to meet the requirements of corrosion resistance, crack resistance (water and air tightness) and the establishment of high pre-compressive stresses, the first time that the circular prestressing of digesters was used in an unbonded prestressing program.

    参考文献
    相似文献
    引证文献
引用本文

Wang Changxiang, Han Qunfang Application of Unbonded Prestressing Technology in the Design of Large Diameter Sludge Digestion Tank. Prestress Technology 2001,5(05X):34-36. 10.59238/j. pt.2001.05X.008

复制
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2023-08-11
  • 出版日期: